Report 3: 2026–27

Major projects 2026

This report provides insights into Queensland’s major infrastructure projects, capital expenditure program, and the key risks and challenges affecting project delivery. 

Overview

Queensland's growth relies on strong infrastructure investment that supports economic development and improves quality of life for Queenslanders. To meet current and future needs, the Queensland Government allocates significant funding to major projects. However, government must manage challenges such as labour shortages, rising costs, and competition for resources to ensure the effective delivery of a growing capital program.

Tabled 16 November 2026.

Elim Beach

Report on a page

Queensland is delivering a large infrastructure program designed to meet long-term growth needs across the state. The Queensland Government’s 2026–27 capital statement – which details spending on long-term infrastructure assets – includes $119.2 billion of planned capital expenditure over the next 4 years.

This report provides insights into Queensland’s major infrastructure projects, project planning and oversight processes, and how it manages infrastructure delivery risks.

Queensland’s capital program is changing

The $119.2 billion the government plans to spend on capital projects over the next 4 years represents an increase of $2.4 billion from the 2025–26 budget. While planned expenditure has increased, the combined total estimated cost of projects reported in the capital statement has fallen from $153 billion to $127.8 billion. The decrease largely reflects a change in how some major energy projects are reported while their full costs are being re-assessed. For these projects, the capital statement reports costs incurred to date and 2026–27 budget estimates, rather than the full estimated cost to complete the projects. The decrease does not reflect a reduction in project scope or funding.

Transport infrastructure now accounts for a larger share of the state’s infrastructure pipeline, while health infrastructure and Brisbane 2032 Olympic and Paralympic Games (Brisbane 2032) investments are also significant components of future expenditure. Of the $7.1 billion allocated to Brisbane 2032 venues, $6.6 billion is forecast to be spent beyond the next 12 months.

More than 60 per cent of reported project costs relate to expenditure beyond the next 12 months, reflecting the long-term nature of major capital projects.

Cross River Rail is moving into testing and commissioning

Cross River Rail has progressed from major construction to integration, testing, and commissioning phases. The Cross River Rail Delivery Authority has completed negotiations with major contractors, and the project's estimated total cost remains at $19 billion. This cost includes the core rail project and a range of associated works, including station upgrades and a new signalling system.

The focus has shifted to integrating trains, stations, signalling, and operating systems before passenger services start. Further testing, staff training, operational readiness activities, and safety assurance processes are required before the railway can enter service. Passenger services are scheduled to commence in 2029.

As the project moves towards being operational, effective planning, governance, and coordination across responsible entities will be critical. Our Forward work plan 2026–29 includes an audit we plan to table in 2028, examining how effectively the Cross River Rail Delivery Authority, the Department of Transport and Main Roads, and Queensland Rail are planning to operationalise Cross River Rail.

Most major projects are in early stages of development

Many of the state's largest projects remain in the early stages of development. Around half of the total estimated cost of projects valued at more than $500 million are still in pre-procurement phases. This means their project scope, delivery models, procurement approaches, and cost estimates are still being refined. Many Brisbane 2032 venue and transport projects are also still in planning, procurement, or approval phases with 6 of 17 venues having progressed to design or early works.

When delivery starts on more of the Brisbane 2032 infrastructure, it will increasingly compete with Queensland's broader infrastructure pipeline for labour, contractors, and construction materials.

This competition between the projects will increase the risk of cost escalation, schedule delays, and difficulties in meeting demands. Effective planning, cost estimation, project oversight, and workforce management will be important in managing these risks. The successful delivery of Queensland's infrastructure program relies on a workforce that is already under pressure, and industry forecasts indicate workforce shortages are likely to continue throughout the decade.

Elim Beach

1. Insights into Queensland’s major projects

Local, state, and federal governments provide funding to support Queensland’s growth, renewal, and development. This funding helps to deliver infrastructure across regions, maintain and upgrade existing assets, support service delivery, and prepare for major events such as the Brisbane 2032 Olympic and Paralympic Games (Brisbane 2032).

This chapter provides insights into major projects the Queensland Government has budgeted for each year between 2022–23 and 2026–27. It also highlights trends in project costs, timelines, and infrastructure for Brisbane 2032.

Definition

Capital expenditure: Money spent to buy or build new assets or improve existing assets. This can include land, buildings, infrastructure, or equipment. Examples include building a new school or upgrading roads.

Capital project: A single project, for example, the construction of a bridge.

Capital program: Several capital projects brought together under one program, for example, the construction of several new roads in a particular area.  In this report, we refer to all capital projects and programs as ‘projects’.

Capital program (Budget Paper 3): The 4-year capital spending forecast in the state capital statement (Budget Paper 3).

Capital statement (Budget Paper 3): The annual budget document that provides an overview of the Queensland Government’s infrastructure delivery program and proposed capital outlays.

Total estimated cost: The total capital expenditure expected to complete a project, as per the state capital statement (Budget Paper 3). This may span multiple financial years until the project is complete and represents the whole-of-project costs. It includes the actual expenditure to date, the budgeted expenditure for 2026–27, and forecast expenditure beyond 2026–27.

The Queensland infrastructure planning framework is changing

The Queensland Government is developing Delivering for Queensland: Infrastructure, which will outline its infrastructure priorities and progress to date and aims to strengthen Queensland’s infrastructure planning framework. This follows the Queensland Productivity Commission’s inquiry into the productivity of the construction sector, which made recommendations about prioritising and coordinating public infrastructure projects.

The state government has identified a range of plans and programs that connect to its infrastructure priorities. Figure 1A provides examples of initiatives.

FIGURE 1A
Plans and programs supporting Queensland’s current infrastructure priorities
Infographic showing plans and programs supporting Queensland’s current infrastructure priorities

Compiled by the Queensland Audit Office from Delivering for Queensland: Infrastructure.

1

The state government is aiming to better integrate regional planning and is preparing 13 new regional plans, each to be supported by a regional infrastructure plan. The Far North Queensland Regional Plan and Infrastructure Plan 2026 took effect on 8 May 2026 and is the first plan completed under this integrated approach. The government is drafting regional plans and infrastructure plans for North Queensland and Wide Bay Burnett and reviewing other regional plans across the state. No time frames have been published for completing these plans.

Changes in the total estimated costs of projects within the capital statement

The capital program (Budget Paper 3) shows that the Queensland Government expects to spend $119.2 billion on capital projects over the next 4 years – the forward estimates – including $29.6 billion planned for 2026–27.

Budget Paper 3 also reports the total estimated cost of projects, which includes the actual expenditure to date, budgeted expenditure for 2026–27, and forecast expenditure beyond 2026–27. This represents the whole-of-project cost other than for ongoing programs with annual funding allocations.

In the 2026–27 capital statement, the total estimated cost of all projects is $127.8 billion, compared with $153 billion in the 2025–26 capital statement.

While costs beyond the forward estimates are less certain, the total estimated cost of projects provides useful information on future capital requirements. Figure 1B shows the growth and proportional allocation of total estimated costs for all projects across key government portfolios from 2022–23 to 2026–27. Appendix C lists the entities included in each portfolio.

FIGURE 1B
Total estimated costs of capital statement projects for key government portfolios – proportional allocation for financial years from 2022–23 to 2026–27

Notes:

1 As highlighted throughout this report, the key energy projects of CopperString, Borumba Pumped Hydro Energy Project, and the Gladstone Project had a change in reporting treatment for total estimated cost (TEC) in the 2026–27 capital statement, while these projects were undergoing further assessment. To provide consistency against previous years, a previously reported TEC has been included in this chart.

2 The figures above represent the total estimated costs, including amounts already spent, budget-year spend, and forecast post budget-year spend. This excludes ongoing programs with annual funding allocations.

3 The entities included in each portfolio may have changed due to machinery of government changes. The portfolios above reflect the 2026–27 names.

4 Energy projects are delivered by energy government owned corporations, reported under the Queensland Treasury portfolio, except for CopperString, which is being delivered by QIC Limited.

5 ‘Other’ includes portfolios such as Education, Queensland Corrective Services, Youth Justice and Victim Support, and Local Government, Water and Volunteers.

Compiled by the Queensland Audit Office from capital statements from 2022–23 to 2026–27.

1

The Transport and Main Roads portfolio remains the largest infrastructure portfolio, with total estimated costs increasing from $63.9 billion in 2025–26 to $77.9 billion in 2026–27. The $14 billion increase largely reflects continued investment in major infrastructure projects, such as Queensland Government commitments towards the Gold Coast Transport Plan, The Wave (Stages 2 and 3), and the Mooloolah River Interchange (Stages 1 and 2). 

Consistent with Budget Paper 3, the reported total estimated costs for the Borumba Pumped Hydro Energy Storage Project and CopperString project include expenditure incurred to date and forecast expenditure to 2026–27, but do not include the full costs of project delivery. This has resulted in the Energy portfolio showing a decrease in total estimated costs from $41.6 billion to $6.4 billion.  These projects account for $30.6 billion of the $35.2 billion decrease. 

Costs beyond 2026–27 remain subject to further assessment and have not yet been fully determined. As a result, these future costs are not included in the portfolio's reported total estimated costs. The Borumba Pumped Hydro Energy Storage Project is progressing through detailed business case development, while CopperString is proceeding under revised delivery arrangements, including the transfer of project delivery responsibility to QIC Limited and changes to funding arrangements.  

The State Development, Infrastructure and Planning portfolio’s total property, plant and equipment costs decreased from $10.2 billion in 2025–26 to $7.3 billion in 2026–27. The decrease is largely due to the reclassification of the state’s $3.5 billion Games Athlete Villages project from property, plant and equipment to capital grants. This reflects the planned delivery of the villages through private-sector partners rather than direct state ownership and delivery.

The decrease is partly offset by increases in the:

  • Land Activation Program – designed to accelerate housing delivery across the state by using government-owned land
  • Northshore Hamilton – a riverfront urban renewal project
  • Industrial Land Acceleration Program – an initiative designed to bring development-ready industrial land to market in regional and high-growth areas.

The 2032 Games Venues Program remains the portfolio's largest project, with a total estimated cost of $5.6 billion.

Queensland Health is another major component of the infrastructure program, with total estimated costs decreasing from $21.5 billion to $19.9 billion. The portfolio continues to have a pipeline of hospital and health infrastructure projects across the state.

Planned capital expenditure is closer to previous budgets

Figure 1C shows the planned capital expenditure reported in each year's capital statement, including the proportion spent to 30 June and the proportion expected to be spent in the short and longer term.

FIGURE 1C
Planned capital expenditure of capital statement projects for financial years from 2022–23 to 2026–27

Notes:

1 The figures above represent the total estimated costs, including amounts already spent, budget-year expenditure, and forecast post-budget-year expenditure. This excludes ongoing programs with annual funding allocations.

2 ‘Expenditure as at 30 June’ represents the estimated actual expenditure at the beginning of the budgeted financial year.

Compiled by the Queensland Audit Office from capital statements from 2022–23 to 2026–27.

1

The expected annual spend for the state increased in 2024–25 and has continued to increase with each budget.

The composition of planned expenditure beyond the next 12 months has changed due to changes in energy related expenditure and approximately 40 per cent relates to 4 major programs: Major Hospital Infrastructure, State Road Network Upgrades – South Coast (road upgrades across the Gold Coast, Logan, and Scenic Rim region), the 2032 Games Venues Program, and the Bruce Highway Targeted Safety Program (a joint Queensland and Australian Government initiative aimed at improving safety along the highway between Gympie and Cairns).

Changes in the profile and composition of planned expenditure may also affect the capability and capacity required to deliver the state's infrastructure program. The delivery of several large and complex programs over the same period can place additional pressure on workforce, contractor, and supply chain availability.

Risks and challenges of delivering projects

The scale and concentration of Queensland's infrastructure program creates a range of delivery risks and challenges. Many projects are being delivered concurrently, and some have fixed delivery timelines. Pressures from labour shortages, cost escalation, supply chain constraints, and competition for specialised skills are greatest when several large projects compete for the same workforce, contractor resources, and construction materials.

Access to skills and experience

Major infrastructure projects depend on a workforce with the skills, experience, and capacity to deliver projects on time and within budget. They also depend on sufficient productivity of the workforce.

Infrastructure Australia, the Australian Government’s independent infrastructure adviser, continues to identify shortages in occupations critical to infrastructure delivery, including engineers, project managers, tradespeople, and labourers. National labour market data also indicates ongoing recruitment difficulties across many technical and trade occupations.

The Queensland Government is responding to the risks through procurement, workforce development, and labour mobility activities.

Industrial relations

Industrial relations matters can pose risks to project delivery. During 2026, the Queensland Commission of Inquiry into the CFMEU and Misconduct in the Construction Industry examined how disruptions on major projects, including Cross River Rail, contributed to delays, additional costs, and reduced productivity. The inquiry has not yet reported its findings.

Capital grants add to the infrastructure delivery pipeline

Capital grants provide funding for infrastructure delivered by entities outside the Queensland Government sector. These include local governments; non-government entities such as local sporting clubs, non-state schools, and student hostels; and individuals, through external contractors. The grants support projects such as roads, housing, community facilities, and water infrastructure that contribute to economic growth and community outcomes.

Yearly budgeted expenditure on capital grants has more than doubled over the last 5 years, from approximately $2.5 billion in 2022–23 to $5.7 billion in 2026–27. Figure 1D shows the major programs contributing to capital grant expenditure over this period.

FIGURE 1D
Capital grants by program – financial years from 2022–23 to 2026–27

Notes:

1 The figures above represent the budgeted expenditure for each financial year. This includes ongoing programs.

2 Capital grants with budgeted expenditure of $200 million or more are shown individually. Capital grants below $200 million are grouped as ‘Other capital grants’.

Compiled by the Queensland Audit Office from capital statements from 2022–23 to 2026–27.

1

Disaster Recovery Funding Arrangements remained the largest capital grant program, with $1.5 billion budgeted in 2026–27, and the Residential Activation Fund accounting for a further $500 million. This Residential Activation Fund is part of the wider $2 billion program across multiple years.

The government plans to deliver the 2032 Games Athlete Villages in partnership with the private sector. It has budgeted $348 million for the program in 2026–27 within the overall $3.5 billion total estimated cost.

Other significant long-term capital grant programs include $1.5 billion for the 2032 Games Venues Program, $390 million for the Cairns Water Security Project, and $216 million for Social and Affordable Housing.

These capital grant programs facilitate delivery by the private sector and other government sectors but also add to the competition for labour and resources for major projects across the state.

Queensland’s largest capital projects

The Queensland state budget provides details of capital projects by portfolio, including each project’s scope, total estimated cost, and expenditure to date. These projects are reported annually in the capital statement.

Figure 1E shows the state’s largest capital projects, each with total estimated costs over $500 million, as of 30 June 2026. It shows expected completion dates based on agency responses, the budgeted estimated costs, and expenditure to 30 June 2026, as reported in the 2026–27 capital statement (released in June 2026).

Definition

Budgeted estimated cost to date: Represents how much a project (or stage of a project) is expected to cost from commencement to completion. In some cases, this may instead represent the allocated budget to date, with further consideration from business cases needed to reach a final cost estimate.

Expenditure to 30 June 2026: Represents the estimated actual expenditure spent on the project per the 2026–27 capital statement.

Announced estimated completion date: The year when the project is expected to be complete and/or operational. In some cases, this represents the completion date for a particular phase of the project, rather than the capital project in its entirety. The completion date is provided by the delivery agencies for each project.

Status: Represents the progress made towards each project as of 30 June 2026. Projects can go through multiple phases (such as early works, tendering and procurement, design, construction, commissioning, and completion). The status is provided by the delivery agencies for each project.

FIGURE 1E
Projects budgeted for more than $500 million – as of 30 June 2026
ProjectBudgeted estimated cost to dateExpenditure to 30 June 2026Announced estimated completion dateStatus
Transport and Main Roads
Icon of a train

Cross River Rail

$9.8 bil.$8.4 bil.2029

Construction in progress.

In 2025, the budgeted estimated cost to date was $8 bil.

Icon of a road

Bruce Highway Targeted Safety Program

$9 bil.$319 mil.2030Design and construction works are underway.
Icon of a train

Logan and Gold Coast Faster Rail

$5.8 bil.$1.3 bil.2031

Construction is in progress on the road over-rail bridge at Kuraby and the relocation of Loganlea station.

Design and preconstruction works are in progress for other precincts.

Icon of a train

The Wave (Stage 1)

$5.5 bil.$194 mil.2032

Design development and procurement activities are underway.

In 2025 it was a planned project and not yet contractually committed.

Icon of a train

Queensland Train Manufacturing Program

$4.9 bil.$2.2 bil.2032

Construction is in progress on train manufacturing and rail facilities.

Manufacturing of the first train is underway.

Icon of a road

Coomera Connector (Stage 1), Coomera to Nerang

$3.5 bil.$2.2 bil.TBD

Stage 1 North opened to traffic in December 2025.

Construction is in progress for the Stage 1 Central and South packages.

Icon of a road

Rockhampton Ring Road

$2 bil.$721 mil.2030Construction is in progress.
Icon of a train

Gold Coast Light Rail (Stage 3), Broadbeach South to Burleigh Heads

$1.6 bil.$1.3 bil.2026Passenger services commenced in August 2026. Finishing works are in progress.
Icon of a train

European Train Control System Signalling Program: Phase 1 (pilot line, tunnel, and Sector 1 to Moorooka)

$1.4 bil.$897 mil.2029

Testing is in progress.

In 2025 the budgeted estimated cost to date was $1.3 bil.

Icon of a train

Beerburrum to Nambour Rail Upgrade (Stage 1)

$1 bil.$399 mil.2027Main construction works are expected to be complete in late 2027. Final testing and commissioning will occur in early 2028.
Icon of a road

Inland Freight Route (Charters Towers to Mungindi), funding allocation

$1 bil.$102 mil.2033Early works are in progress. Planning and design works are underway for various priority sections along the Inland Freight Route.
Icon of a road

Gateway Motorway, Bracken Ridge to Pine River upgrade

$1 bil.$155 mil.TBD

Detailed design is underway. Construction is expected to commence in late 2026.

In 2025 it was a planned project and not yet contractually committed.

Icon of a road

Bruce Highway (Brisbane–Gympie), Gateway Motorway to Dohles Rocks Road upgrade (Stage 1)

$948 mil.$139 mil.TBD

Detailed design is underway. Construction is expected to commence in late 2026.

In 2025 it was a planned project and not yet contractually committed.

Icon of a road

Road Safety Infrastructure 2026–27 to 2029–30

$787 mil.$94 mil.TBDDesign and construction underway for various projects improving road safety infrastructure.
Icon of a train

Clapham Yard Stabling (Moorooka), construct
stabling yard

$887 mil.$410 mil.2029

Construction is in progress.

In 2025 the budgeted estimated cost to date was $693 mil.

Icon of a train

New Gold Coast Stations (Pimpama, Hope Island, and Merrimac)

$591 mil.$475 mil.2027

Pimpama station and Hope Island stations opened in October 2025 and May 2026 respectively. Construction is in progress for Merrimac station.

In 2025 the budgeted estimated cost to date was $500 mil.

Icon of a cow

Queensland Beef Corridors, funding allocation

$500 mil.$13 mil.TBDDelivery of an early works package is underway.
Energy
Icon of a hydro energy dam

Borumba Pumped Hydro Energy Storage

$485 mil.$160 mil.TBD

Exploratory works are underway. A refreshed business case and commercial assessment for the proposed Borumba Project is in development.

In 2025 budgeted estimated cost to date was $18.4 bil. The total estimated cost in Budget Paper 3 reflects expenditure to date and forecasted expenditure in 2026–27. It does not represent the full final project cost.

Icon of an electrical pylon

CopperString

$1.2 bil.$752 mil.2032

QIC is delivering CopperString with major construction on the Eastern Link.

In 2025 budgeted estimated cost to date was $13.9 bil. The total estimated cost in Budget Paper 3 reflects expenditure to date and forecasted expenditure in 2026–27. It does not represent the full final project cost.

Icon of two wind turbines

Wambo Wind Farm (Stage 1 and Stage 2)

$921 mil.$847 mil.2027

Practical completion of Stage 1 is forecast for November 2026.

Practical completion of Stage 2 is forecast for the first quarter of 2027.

Icon of an electrical pylon

Gladstone Project

$685 mil.$184 mil.2029 (Stage 1)
2030 (Stage 2)

Stage 1 has received Ministerial Infrastructure Designation, with initial site clearing and preparation underway.

In 2025 the budgeted estimated cost to date was $2.5 bil., aligned to Powerlink’s Final Assessment Report at that time.

The total estimated cost in Budget Paper 3 reflects expenditure to date and forecast expenditure in 2026–27. It does not represent the full final project cost.

Icon of a battery

Stanwell Battery

$648 mil.$556 mil.2027

Construction is in progress.

In 2025 the budgeted estimated cost to date was $688 mil.

Icon of an electrical pylon

System Strength Project – synchronous condensers

$597 mil.$141 mil.2029Construction is due to start in 2027.
Queensland Health
Icon of a hospital

Major Hospital Infrastructure

$17.2 bil$2.8 bil.Various

Commitment captures multiple capital projects, each with individual project timelines.

In 2025 the budgeted estimated cost to date was $13.4 bil.

Icon of a hospital

Other Hospital Car Parking Program

$914 mil.$53 mil.Various

Commitment captures multiple capital projects, each with individual project timelines.

In 2025 the budgeted estimated cost to date was $1.2 bil.

Icon of a hospital

Building Rural and Remote Health Program

$591 mil.$411 mil.VariousCommitment captures multiple capital projects, each with individual project timelines.
Other
Icon of a jail cell

Arthur Gorrie Correctional Centre

$1.3 bil.$28 mil.2032Managing contract awarded for Stage 1. Design development in progress.
Icon of a jail cell

Townsville Correctional Centre

$1.1 bil.$23 mil.2030Managing contract awarded for Stage 1. Design development in progress.
Icon of a dam

Paradise Dam Improvement Project

$4.4 bil.$293 mil.TBDSunwater has submitted its Paradise Dam detailed business case to the Queensland Government.
Icon of a tap with a drop of water coming out of it

Fitzroy to Gladstone Pipeline

$983 mil.$945 mil.2026Construction is in progress. Completion and operation are expected in 2026.
Icon of a jail cell

Woodford Youth Detention Centre

$983 mil.$688 mil.2028Construction is in progress. An expansion option has been activated, delivering an additional 32 beds.
Icon of a dam

Somerset Dam Improvement Project

$515 mil.$165 mil.TBDBusiness case development is in progress, with a submission to the Queensland Government expected early 2027.
State Development, Infrastructure and Planning
Icon of a stadium

2032 Games Venues Program

$7.1 bil.1$64 mil.2032Project validation reports and planning are in progress. Some venues are in design development, procurement, or early works.
Icon of a collection of city buildings

Northshore Hamilton

$668 mil.$173 mil.TBDConstruction is expected to commence in 2028.

Notes:

TBD – To be determined.

1 The total $7.1 billion program is made up of $5.6 billion in property, plant and equipment and $1.5 billion in capital grants, including budget provisions, pending government consideration of venue projects.

Compiled by the Queensland Audit Office from the 2026–27 capital statement for various state government entities.

1

Major rail projects across Queensland are underway

Several major rail projects are underway in Queensland, including The Wave (Stage 1), Logan and Gold Coast Faster Rail, the Queensland Train Manufacturing Program, and the Gold Coast Light Rail (Stage 3) project. Figure 1F provides a summary of each project’s budget and total expenditure to date.

FIGURE 1F
Major rail projects across Queensland (estimated expenditure as of 30 June 2026)
Infographic describing the major rail projects across Queensland (estimated expenditure as of 30 June 2026)

Compiled by the Queensland Audit Office from information provided by the Department of Transport and Main Roads and from the 2026–27 capital statement.

1

The Wave (Stages 1, 2, and 3)

The Wave – previously known as the Direct Sunshine Coast Rail Line – is a public transport project that will connect Beerwah and the Sunshine Coast Airport. The project is made up of 3 interconnected components, as shown in Figure 1G:

FIGURE 1G
Stages of The Wave
Three-stage diagram Stage 1 (Rail): Build 19 km of dual-track rail, with new stations at Aura (Bells Creek) and Caloundra, and upgrades to Beerwah station. Stage 2 (Rail): Extend the rail line from Caloundra to Birtinya, with stations at Aroona and Birtinya. Stage 3 (Metro): Provide a metro-style public transport service connecting Birtinya to Maroochydore and Sunshine Coast Airport. Includes Mooloolah River Interchange Upgrade

Compiled by the Queensland Audit Office from information provided by the Department of Transport and Main Roads.

1

Stage 1 has progressed from a planned investment to a contractually committed project, supported by a $5.5 billion joint funding commitment shared equally by the Australian and Queensland governments. Stages 2 and 3 are partially funded by the Queensland Government to continue critical path works along with the Mooloolah River Interchange Upgrade.

Design and pre-construction activities for Stage 1 started in mid-2026, following the award of key contracts, including signalling works. Procurement for Stages 2 and 3 are underway, with contracts expected to be awarded in late 2026. All stages are planned to be delivered concurrently, with major construction expected to begin in early 2027, subject to approvals. 

The Mooloolah River Interchange Upgrade moved into early construction during 2025–26, with site preparation and embankment works starting in June 2026 to support its connection to Stage 3.

Logan and Gold Coast Faster Rail

The Logan and Gold Coast Faster Rail project involves expanding approximately 20 kilometres of the rail corridor between Kuraby and Beenleigh from 2 tracks to 4. 

The project is intended to support additional rail services between Brisbane and the Gold Coast. The approved budget remains $5.75 billion, jointly funded by the Australian and Queensland governments, with each contributing $2.875 billion.

During 2025–26, the project began site investigations and design activities. Community engagement on updated station precinct designs and proposed works along the corridor continued. 

Construction is underway on the relocation of Loganlea Station and is expected to be completed in 2027. Work has also commenced on replacing the Beenleigh Road level crossing at Kuraby with a road-over-rail bridge and associated road upgrades. Proposed level crossing removals at Woodridge, Bethania, Holmview, and Beenleigh remain in design and consultation stages.

Planning and design have also started for the European Train Control System – a new train signalling system – enabling works and the extension of the Holmview cattle siding. The overall project is expected to be completed by 2031. 

Queensland Train Manufacturing Program

The Queensland Train Manufacturing Program (QTMP) includes 65 new 6-car passenger trains, a manufacturing facility at Torbanlea, and a maintenance facility at Ormeau. It also provides supporting infrastructure, which includes road upgrades, rail connections, train testing facilities, additional train storage, and signalling upgrades.

FIGURE 1H
Queensland Train Manufacturing Program
Infographic showing statistics on the Queensland Train Manufacturing Program - $4.9 bil total captial costs; $4.6 bil. contract awarded to Downer; 2032 all trains in services; $2.2 bil. total expenditure to date (30 June 2026); Queensland Government contribution $9.5 bil.

Compiled by the Queensland Audit Office from information provided by the Department of Transport and Main Roads and from the 2026–27 capital statement.

1

In June 2023, the state committed $7.1 billion to the program following completion of the business case. This included funding for train manufacturing, maintenance facilities, stabling, and an initial 15 years of maintenance. At the same time, the estimated total program cost increased to $9.5 billion due to the expanded scope and the higher labour and supply costs identified through the procurement process.

The reported program cost figures differ due to scope, underlying assumptions, and reporting time frames. The $4.9 billion amount within the capital statement represents the program’s total capital cost, while the $4.6 billion Downer contract covers design, construction, manufacturing, and 15 years of fleet maintenance.

The $9.5 billion total Queensland Government contribution also includes 20 years of operations and maintenance, additional stabling yards, program management costs, and a contingency. The 2021 business case estimate of $7.1 billion, used for budgeting purposes, excluded this additional scope.

To date, more than $690 million has been spent on local rollingstock goods and services, and 6 companies have established regional operations. A Manufacturing Centre of Excellence opened in Maryborough in late 2025 to support workforce training and skills development. High rainfall affected construction of the Ormeau Rail Facility during 2024–25; however, construction continued and fit-out of the main maintenance building is in progress.

Train production has started at the Torbanlea manufacturing facility, the rest of the facility is expected to be fully operational in early 2027. Two prototype trains built in South Korea by Hyundai Rotem Corporation – Downer’s rollingstock joint venture partner – are expected to arrive in Australia in late 2026. 

The prototypes have informed manufacturing planning for the Torbanlea facility and are expected to be used for testing on the South East Queensland rail network. The first QTMP train is expected to be ready to enter passenger service in 2027, with all 65 trains to be available for Brisbane 2032.

Figure 1I provides an overview of program progress, including train production, construction of the Torbanlea and Ormeau facilities, supporting infrastructure works, and key delivery milestones.

FIGURE 1I
Progress of the Queensland Train Manufacturing Program
Icon of a train on tracks

Train manufacturing facility

Location marker icon

Torbanlea

  • The facility includes dedicated areas for carriage assembly, electrical fit-out, bogie construction (the wheeled undercarriage of a train), and train testing.
  • Train manufacturing started at Torbanlea in June 2026. The Torbanlea facility is expected to be fully operational in 2027.
  • The first train is expected to be ready to enter passenger services in 2027, with all 65 trains expected to be in service by 2032.
Icon of a checklist document

Rail facility

Location marker icon

Ormeau

  • The facility will maintain the new train fleet and provide stabling for up to 20 6-car trains.
  • Rail installation and internal fit-out works are underway. The facility will connect to the Gold Coast rail line at its northern and southern ends.
  • Construction activities are continuing throughout 2026 and are expected to be completed in line with delivery of the QTMP trains.
Icon of chain links

Other works

  • Supporting works include rail connections, testing and signalling infrastructure, additional train stabling, and upgrades to Goldmine Road.
  • The Goldmine Road works include road widening, drainage improvements, and a new signalised intersection providing access to the Ormeau facility.

Compiled by the Queensland Audit Office from information provided by the Department of Transport and Main Roads.

1

Gold Coast Light Rail (Stage 3)

Gold Coast Light Rail is being delivered in stages. The dual-track network spans 27 kilometres and includes 27 stations from Helensvale to Burleigh Heads. This includes the newly completed Stage 3 – a 6.7-kilometre southern extension from Broadbeach South to Burleigh Heads and 8 new stations.

During 2025–26, Stage 3 completed testing and commissioning activities, including full-line testing. Passenger services began on 9 August 2026, with 8 new stations opening along the extension. Following commencement of passenger services, the project transitioned from delivery to operational service.

Gold Coast Light Rail Stage 4 update

The Gold Coast Light Rail Stage 4 was a proposed 13-kilometre extension from Burleigh Heads to Coolangatta via the Gold Coast Airport. Following a review undertaken by the Department of State Development, Infrastructure and Planning, which included a round of public consultation, the Queensland Government decided not to proceed with the project.

The review's findings will inform future transport planning for the Gold Coast. In the interim, bus service improvements are planned while a broader transport study is underway.

Gold Coast Transport Plan

As part of the 2026–27 state budget, planning funding was provided for 2 major transport projects under the Gold Coast Transport Plan including:

  • an extension of the Gold Coast Light Rail connecting Harbour Town at Biggera Waters to Gold Coast University Hospital, and;
  • a proposed high-frequency public transport service connecting Robina and Coolangatta via Varsity Lakes, Burleigh Heads, and the Gold Coast Airport.

The rail corridor will also be preserved from Varsity Lakes down to the Gold Coast Airport to allow for future expansion of the line.

Queensland is implementing a range of road safety and infrastructure projects

A range of road safety and transport infrastructure projects are underway across Queensland, including targeted safety initiatives and major road upgrades to address transport demand and network requirements.

Bruce Highway Targeted Safety Program

The $9 billion Bruce Highway Targeted Safety Program is comprised of road safety upgrades along the highway between Gympie and Cairns. Works include providing wider centre lines, upgrading road surfaces, and intersections, building overtaking lanes and rest areas, and upgrading narrow bridges. An initial $300 million early works package funded the start of the delivery of the program.

As of September 2026, the program has delivered 18 completed projects, with a further 15 under construction and 10 expected to progressively start from mid-2026.

Procurement activities have also progressed, with 22 design and construction tenders released and a further 52 tenders announced. Contractor panels have been established to support program delivery. Planned works focus on sections of the highway with a poor safety record and include key safety treatments.  

The program is funded by the Australian and Queensland governments, which have committed $7.2 billion and $1.8 billion respectively. Works are expected to continue through to 2030.

Targeted Road Safety Program

The Targeted Road Safety Program continued across Queensland during 2025–26 through initiatives such as the Safer Roads Sooner, Black Spot, Asset Management, and School Transport Infrastructure programs. It included 44 new Black Spot projects and additional safety works at identified high-risk locations.

The Queensland Transport and Roads Investment Program 2026–27 to 2029–30 includes $1.6 billion for targeted road safety initiatives.

Coomera Connector (Stage 1)

Coomera Connector Stage 1 is a new 16-kilometre motorway between Coomera and Nerang, delivered in 3 packages – north, central, and south. Stage 1 North (Shipper Drive to Helensvale Road) opened to traffic on 2 December 2025. The Stage 1 Central (Helensvale Road to Smith Street Motorway) and Stage 1 South (Smith Street Motorway to Nerang-Broadbeach Road) packages are currently under construction.

The project’s budget increased from $2.2 billion to $3.5 billion due to construction cost escalation, environmental approval requirements, complex ground conditions, and changes in project scope. The Australian Government also increased its contribution from $1.5 billion to $1.75 billion, resulting in equal contributions of $1.75 billion from the Australian and Queensland governments.

Rockhampton Ring Road

The Rockhampton Ring Road is 17.4 kilometres of new roadway, including a third crossing of the Fitzroy River and an Alexandra Street overpass. Main construction is underway.

During 2025–26, the Limestone Creek and Lion Creek bridges were completed, and the Rockhampton–Ridgelands Road roundabout opened to traffic. The project includes 18 bridges along the main ring road alignment, including 8 road overpasses and 7 water crossings. Major works are underway on the Fitzroy River crossing and associated structures.

The project budget remains $1.98 billion, funded by the Australian and Queensland governments, with contributions of $1.4 billion and $580 million respectively. The budget includes delivery of the Alexandra Street overpass.

Pacific Motorway, Varsity Lakes to Tugun upgrade

Construction on the $1.5 billion Pacific Motorway (M1) Varsity Lakes to Tugun Upgrade started in 2020 and was completed in November 2025. The project widened the 10-kilometre section of the M1 between Varsity Lakes and Tugun to provide at least 3 traffic lanes in each direction.

Works included motorway widening, interchange and bridge upgrades, smart motorway technology, and active transport connections. The Australian and Queensland governments each contributed $750 million towards the project. 

Queensland’s major hospital infrastructure is now managed as a single program

The Queensland Government’s Hospital Rescue Plan was established following an independent review of the former Capacity Expansion Program. The program includes 3 new hospitals, major hospital expansions, and other health infrastructure projects across Queensland.

Masterplans for key projects, including the Townsville University Hospital Expansion, new Toowoomba Hospital, new Coomera Hospital, Redcliffe Hospital Expansion, and new Bundaberg Hospital, were finalised in December 2025.

Procurement, planning, and design activities continued during 2025–26, while several other hospital expansion projects progressed through construction and delivery planning.

The presentation of these projects in the capital statement (Budget Paper 3) changed in 2026–27. In the 2025–26 capital statement, 6 hospital expansion projects were reported as separate budget line items to consolidate reporting of capital funding for like projects. In the 2026–27 capital statement, these projects are reported as a single line item – Major Hospital Infrastructure – reflecting their inclusion within the broader Hospital Rescue Plan. This consolidation requires consideration when comparing with prior budget reporting.

While the 2026–27 capital statement now provides higher level information, the Hospital Rescue Plan outlines the scope, timing, and delivery status of major health infrastructure projects across Queensland. This includes new hospitals, hospital expansions, and other health infrastructure works, providing an alternate source of information on the state's major hospital infrastructure program.

Queensland’s energy projects are changing under a new roadmap

Since the release of the Queensland Government’s Energy Roadmap (the roadmap) in October 2025, the scope, sequencing, and delivery arrangements of several major energy projects have changed. Some projects are undergoing further assessment, while others have been restructured, staged, or transferred to new entities.

These changes are reflected in project budgets and expenditure profiles. Planned capital expenditure on energy infrastructure decreased by $1.2 billion, from $6.7 billion in 2025–26 to $5.5 billion in 2026–27, reflecting revised project priorities, timing, and delivery arrangements across the sector. Figure 1J shows key infrastructure projects planned or in progress as part of the roadmap.

FIGURE 1J
Key infrastructure projects of the Energy Roadmap
Infographic showing the key infrastructure projects of the Energy Roadmap

Compiled by the Queensland Audit Office from the 2026–27 capital statement.

1

CopperString

The CopperString project involves the proposed delivery of more than 1,100 kilometres of electricity transmission infrastructure across 2 sections – the Eastern Link between Townsville and Hughenden, and the Western Link between Hughenden and Mount Isa.

Following the release of the Queensland Government’s Energy Roadmap in October 2025, the project’s delivery approach was revised, with construction of the Eastern Link accelerated and enabling works beginning on the Western Link. Responsibility for project delivery transferred from Powerlink to a new QIC‑managed delivery entity. During the transition, Powerlink has continued to support with approvals, easements, and early works activities.

Other developments included establishing the $200 million North West Energy Fund, the start of early works, and construction commencing on the $225 million Flinders Substation.

The Queensland Government’s total funding commitment increased from $2.4 billion in 2025–26 to $3.2 billion in 2026–27.

Although the project's total estimated cost was reported as $13.9 billion in 2025–26, the 2026–27 budget reports $1.2 billion, representing actual expenditure to date and forecast expenditure for 2026–27, but not the total expected cost to complete the project.

The final whole-of-project cost remains subject to further assessment by QIC. Consequently, the reduced amount reported in the budget reflects a change in reporting treatment rather than a reduction in the government's funding commitment.

Subject to approvals, construction of the Eastern Link is scheduled to begin in 2028, with completion expected in 2032.

Gladstone Project

The Gladstone Project is a 2-stage program designed to reinforce Central Queensland’s electricity transmission network. The project includes a new transmission line between Calvale and Calliope River, upgrades to existing substations, a proposed Gladstone West Substation, and a new transmission line to Bouldercombe.

The total estimated cost was $2.5 billion in 2025–26. The 2026–27 capital statement reported $685 million, reflecting expenditure to date and forecast expenditure for 2026–27 given the project was still being assessed through the Priority Transmission Investment regulatory process when the budget was prepared. This does not represent any change in funding approach. The project was subsequently declared a Priority Transmission Investment and approved under the regulatory framework in August 2026.

Stage 1, the Calvale to Calliope River Transmission Line Reinforcement Project, has progressed into procurement and pre-construction. The project received environmental approval from the Australian Government in June 2026 and Ministerial Infrastructure Designation in July 2026.

Stage 2, which includes the Gladstone West Substation and transmission line to Bouldercombe, is subject to planning and environmental approvals. Powerlink is targeting completion of the Calvale to Calliope River transmission line by March 2029, and completion of Stage 2 of the project in the second half of 2030.

Borumba Pumped Hydro Energy Storage

Planning and assessment of the Borumba Pumped Hydro Energy Storage Project is continuing. Federal approval of exploratory works in December 2025 enabled Queensland Hydro to commence geotechnical investigations to support detailed design and preparation of a revised business case.

The project’s reported total estimated cost was $18.4 billion in 2025–26. The 2026–27 capital statement reports an estimate of $484.7 million, comprising expenditure incurred to date and $324.3 million budgeted in 2026–27 for exploratory works and further project development. This amount does not reflect the total expected cost to complete the project.

Queensland Hydro is using the exploratory works program to inform the revised business case and project design. Any decision to proceed to construction remains subject to completion and assessment of the revised business case and a final investment decision.

Brigalow Gas Peaking Plant

The Brigalow Gas Peaking Plant is a 400-megawatt gas-fired peaking power station being developed adjacent to the existing Kogan Creek Power Station near Chinchilla in the Western Downs.

The facility will have 12 gas turbines and is designed to provide fast-start generation, reaching full output within 5 minutes during periods of peak electricity demand.

The project's total estimated cost was reported as $1.05 billion in 2025–26. The 2026–27 capital statement reports $390.9 million, reflecting CS Energy’s gross capital expenditure following an agreement with APA Group in September 2026. This change does not represent a reduction in the overall project cost.

Under the agreement, APA will lead project delivery and hold an 80 per cent ownership interest in the plant, whilst CS Energy will retain a 20 per cent ownership interest and will operate and maintain the plant after completion.

The project is now under construction. In June 2026, the main construction contract for balance-of-plant works was awarded. Early enabling works, including site access roads and an intersection upgrade, have been completed, and bulk earthworks have begun, to prepare the construction site. The project remains on track for operation in 2029 subject to final commissioning.

Planning is underway for future Brisbane Metro expansions

Brisbane City Council, in partnership with the Queensland and Australian governments, is developing a business case for potential future expansions of the Brisbane Metro – an electric bus rapid transit network.

The business case will identify preferred route alignments, depot locations, network improvements, and delivery staging for 4 priority corridors: Northern Metro (CBD to Carseldine), Southern Metro (CBD to Springwood), Eastern Metro (CBD to Capalaba), and Airport Metro (CBD to Brisbane Airport).

The Australian Government supports development of the final business case. The proposal remains in the planning and business case development phase.

Olympic and Paralympic infrastructure projects are in the planning stages

Infrastructure for the Brisbane 2032 Olympic and Paralympic Games

The Queensland Government’s 2032 Delivery Plan sets out an integrated program of Brisbane 2032 venues, transport infrastructure, and supporting investments planned across Queensland.

Delivery is coordinated through a multi-agency model, with the Games Independent Infrastructure and Coordination Authority responsible for leading the delivery of new and upgraded venues and coordinating infrastructure planning across the program.

FIGURE 1K
Major infrastructure programs for Brisbane 2032
Infographic describing major infrastructure programs for Brisbane 2032

Compiled by the Queensland Audit Office from the 2026–27 capital statement.

1

Major venue completion dates are scheduled to allow time for testing, commissioning, and operational readiness activities before the Games. Peak construction activity is expected between 2027 and 2031.

The program is being delivered alongside Queensland’s broader infrastructure pipeline. As Brisbane 2032 projects move into construction, they will compete for labour, contractors, and plant and construction materials required for other major infrastructure projects. Effective planning, procurement, and workforce management will be important to manage delivery risks and support timely delivery.

To provide further insight into arrangements supporting Brisbane 2032 delivery, our Forward work plan 2026–29 includes an audit planned for tabling in early 2027 on cross-entity governance and preparedness for Brisbane 2032.

The report will assess the effectiveness of governance, risk management, and planning arrangements across participating entities, and provide an update on the progress made by entities for delivery of the Games Venues Program. It is the second in our series of reports examining the planning and delivery of Brisbane 2032.

Elim Beach

2. Planning and oversight of Queensland’s major projects

Effective governance, procurement, asset management, and reporting supports public sector entities to deliver capital projects.

This chapter outlines key developments in these areas, including improvements in the availability and quality of capital project information, as well as how entities are applying procurement policies and procedures.

Insights into the delivery of Queensland’s capital projects

Queensland Government departments and statutory bodies use the Project Assessment Framework (PAF) to guide the planning and delivery of major infrastructure projects. The framework includes key decision points and assurance activities designed to support informed decision-making and effective project delivery. Other public sector entities generally apply similar principles where government funding or approval is required.

Figure 2A demonstrates the policies and framework supporting the PAF in delivering Queensland’s largest capital projects.

FIGURE 2A
Component, policy, and framework supporting the Project Assessment Framework (PAF)

Business case development framework

Infrastructure Proposal Development Policy

Gateway reviews

Outlines the step-by-step process for planning and assessing major infrastructure proposals.

Explains how infrastructure proposals are reviewed to ensure they are well planned, backed by evidence, and likely to achieve their intended outcomes.

Provide independent reviews at key points in the project life cycle to identify risks and suggest improvements.

Compiled by the Queensland Audit Office from Queensland Treasury's Project Assessment Framework.

1

The PAF divides the project life cycle into 8 key stages, from identifying a service need through to realising project benefits. These stages support consistent decision-making and alignment with whole-of-government priorities.

At each stage, agencies assess the project’s progress and quality to ensure it aligns with strategic goals and delivers value for money. Projects must meet the requirements of each stage before moving to the next.

Around 50 per cent of the total estimated cost of projects greater than $500 million relates to projects that are in the pre-procurement stage of their life cycle, compared with 64 per cent in 2025–26. At this early stage, project scope, design, delivery models, and market conditions are often still being assessed, resulting in lower cost certainty.

The reduction from 64 per cent to 50 per cent since last year reflects 2 factors: a significant decrease in the total estimated costs of energy projects and the progression of several projects from pre-procurement into post-procurement stages of the project life cycle.

As projects progress through later stages of the project life cycle, total estimated costs generally become more reliable and may increase.

Figure 2B shows the current project life cycle stages as per the PAF for projects over $500 million, grouped by their total estimated cost.

FIGURE 2B
Total estimated costs of capital statement projects over $500 million split by their project delivery stages under the Project Assessment Framework
Infographic describing the total estimated costs of capital statement projects over $500 million split by their project delivery stages under the Project Assessment Framework

Compiled by the Queensland Audit Office from information provided by agencies.

1

Cost certainty increases as projects progress through the Project Assessment Framework

The PAF includes a series of decision points where agencies assess affordability, costs, benefits, risks, and delivery options before progressing to the next stage. The PAF recommends undertaking gateway reviews at each of these key decision points.

Gateway reviews provide independent assurance at key stages of the life cycle to test whether projects are ready to proceed and whether significant risks have been appropriately identified and managed. These reviews are designed to strengthen project planning and provide government with greater confidence in estimated costs and expected outcomes.

Figure 2C shows how project assessment processes and gateway reviews support project planning, cost estimation, and budget management throughout the project life cycle.

FIGURE 2C
How project assessment processes and gateway reviews help manage project costs and budget risks

PAF stage 

Key budget management activities

Gateway review focus

Contribution to managing costs

Strategic assessment of service requirement

Identify service need, strategic objectives, and potential investment scale

Gate 0 – 
Strategic assessment

Tests whether a genuine service need exists before significant expenditure is incurred

Preliminary evaluation

Develop options, preliminary cost estimates, and economic assessment

Gate 1 – Preliminary evaluation

Challenges assumptions, scope, and affordability; identifies optimism bias and early cost risks

Business case development

Provide detailed cost estimates, risk assessments, cost-benefit analysis, and funding requirements

Gate 2 – 
Business case

Validates cost estimates, economic benefits, and contingency provisions before approval

Supply strategy development

Evaluate delivery models, procurement strategy and risk allocation

Supporting assurance reviews

Assesses whether delivery and contracting approaches appropriately allocate cost and delivery risks

Source supplier(s)

Undertake tender evaluation and contract negotiations

Gate 3 – 
Contract award

Confirms procurement outcomes represent value for money and remain within approved budgets

Establish service capability

Mobilise and plan implementation

Gate 4 – 
Readiness for service

Reviews preparedness for delivery and identifies emerging cost pressures

Deliver service

Monitor delivery, forecasts, and contract performance

Ongoing project controls

Tracks budget variances and movements in forecast costs

Benefits realisation

Assess achievement of intended outcomes

Gate 5 – 
Benefits realisation

Provides lessons learnt to improve future estimating and project planning

Compiled by the Queensland Audit Office from Queensland Treasury's Project Assessment Framework, Cost-Benefit Analysis Guidelines, and Gateway Review Process.

1

Gateway reviews are most effective at key decision points in the project life cycle, particularly during preliminary evaluation, business case development, and supply strategy development. At these points the project scope, cost estimates, procurement approaches, and risks are still being refined, which provides an opportunity to identify and address issues early. However, gateway reviews can continue to provide value throughout project delivery.

Independent reviews at these stages can strengthen decision-making, improve the quality of cost estimates, and identify risks before major funding and procurement decisions are made.

Cost overruns can occur throughout the project life cycle

Cost overruns can occur for a range of reasons throughout the project life cycle. We have published a blog on how entities can better manage the risks that contribute to budget overruns in major projects: www.qao.qld.gov.au/blog/understanding-why-budget-overruns-occur-how-prevent-them.

In this blog, we examine common causes of budget overruns, including:

  • insufficient early-stage planning
  • unrealistic cost estimates
  • poorly defined scope
  • weak project controls
  • contract variation risks
  • governance weaknesses.

We also provide information to help support entities’ planning, budgeting, risk management, procurement, contract management, and project governance practices (such as project assurance reviews) to improve cost certainty and project outcomes.

Understanding the factors that drive budget escalation can help agencies focus their project development, risk management, and gateway review processes on areas most likely to affect project costs, schedules, and delivery outcomes.

Agencies have opportunities to strengthen their oversight of major project budgets

Queensland Treasury's cost-benefit analysis guidance recommends that agencies systematically assess project costs, benefits, risks, and alternative options throughout project development. This analysis supports evidence-based decision-making and helps agencies better understand potential financial risks before they seek funding approval.

With around half of the total estimated cost of projects exceeding $500 million still in pre-procurement stages, effective project assurance is important. Figure 2D highlights the potential benefits of gateway reviews.

FIGURE 2D
Potential benefits of gateway reviews

Improve reliability of early project cost estimates

Strengthen visibility and oversight of budget movements throughout the project life cycle (including PAF stages)

Increase transparency and accountability for significant budget changes

Drive improvements in project governance, planning, and risk management through independent assurance

Improve cost certainty and delivery performance by identifying and addressing risks early

Promote continuous improvement through the capture and application of lessons learned

Compiled by the Queensland Audit Office from information within the Project Assessment Framework.

1

The Queensland Procurement Policy 2026 has introduced changes to procurement practices

In January 2026, the Queensland Government implemented the Queensland Procurement Policy 2026 (QPP 2026), replacing the previous procurement framework for Queensland public sector agencies.

The QPP 2026 introduces a flexible, risk-based approach to procurement providing a framework of mandatory, recommended, and discretionary requirements. Figure 2E summarises the key changes introduced under QPP 2026.

FIGURE 2E
Key changes of the Queensland Procurement Policy 2026

It replaces requirements with a tiered framework of 'must', 'should', and 'may'.

It replaces the Ethical Supplier Threshold and Ethical Supplier Mandate with the Procurement Assurance Model (a framework for recognising supplier performance and promoting accountability)

It removes Best Practice Industry Conditions (BPICs) for future procurements

It aims to simplify procurement processes for suppliers doing business with government

It aims to support decision making through the introduction of the Better Data, Better Decisions Strategy 2026–2029

It aims to provide clearer responsibilities for managing key areas of government purchasing

Compiled by the Queensland Audit Office from information within the Queensland Procurement Policy 2026.

1

For major infrastructure projects, the most significant impacts are expected during the supply strategy development and source supplier stages of the PAF.

At these stages, agencies determine procurement approaches, engage with the market, and award contracts.

The QPP 2026 places greater emphasis on:

  • forward procurement planning – agencies identify and plan their future purchasing needs early, typically over the next 12 to 24 months
  • category management – agencies group similar goods and services into categories, such as information technology, professional services, fleet, or facilities management
  • supplier engagement – agencies engage with suppliers before, during, and after procurement processes to better understand market capability, emerging solutions, risks, and opportunities
  • proportionality of procurement processes – agencies apply procurement requirements that are appropriate to the value, risk, complexity, and nature of the purchase
  • the achievement of broader economic, environmental, and social outcomes through procurement activities.

The QPP 2026 also introduces the Procurement Assurance Model (PAM), which complements existing project assurance processes. While gateway reviews assess whether projects are strategically justified, affordable, deliverable, and appropriately governed at key decision points, the PAM focuses on procurement performance, supplier conduct, and compliance with procurement policy requirements and the Queensland Government Supplier Code of Conduct 2026.

The QPP 2026 is likely to affect a large portion of Queensland's infrastructure pipeline because one-half of projects are still in the pre-procurement stage. For these projects, agencies may need to review procurement strategies, policies, templates, and governance arrangements to align with the new requirements before carrying out procurement activities.

Projects with contracts already awarded are likely to be more affected by the policy's contract management, supplier performance monitoring, and accountability requirements than by changes to sourcing processes.

The QPP 2026 was released on 11 November 2025 and began on 1 January 2026. Its implementation is occurring in stages. Agencies must publish category strategies (plans that outline procurement priorities and approaches for specific areas of spending) and procurement expenditure information annually from 31 March 2026.

Updated invitation and contract templates are scheduled to be introduced across procurement categories by 31 December 2026, and the PAM incentive scheme – a supplier rating system that is designed to recognise and reward high-performing suppliers – is scheduled to commence on 1 January 2027.

As a result, agencies may have already started or completed some implementation activities.

Icon of a person holding a megaphone

Opportunities for entities – ongoing implementation of QPP 2026

Entities may need to continue to:

  • review and update their procurement policies, procedures, and templates
  • strengthen procurement data and category management practices
  • build workforce capability to support compliance with the new procurement policy.

Entities may also need to continue simplifying procurement processes, improving supplier engagement, maintaining forward procurement planning information, and applying procurement approaches that are proportionate to risk and complexity.

We will include further detail on procurement-related findings and observations in our upcoming report State entities 2026.

The Department of Transport and Main Roads' revised project reporting approach

Alongside changes to procurement practices, agencies have also revised how they report projects. In June 2025, the Department of Transport and Main Roads (TMR) changed how it reports investments in the Queensland Transport and Roads Investment Program 2026–27 to 2029–30 (QTRIP) following a strategic review.

QTRIP is TMR’s rolling 4-year transport infrastructure program, which outlines funded and planned investments across Queensland. These investments are also reported within the TMR portfolio section of the 2026–27 capital statement.

The review examined how TMR manages its infrastructure pipeline and opportunities to strengthen cost and risk management throughout the life of major projects. A key change was the introduction of 2 project classifications: planned and contractually committed. Under this approach, planned projects are reported without a total estimated cost, while contractually committed projects include a total estimated cost.

QTRIP is the second publication under this reporting approach. The distinction between planned and contractually committed projects provides information on where projects sit within the infrastructure pipeline. The program includes $46.9 billion of contractually committed investments across road, rail, maritime, and public transport infrastructure.

Significant contractually committed investments include the Bruce Highway Targeted Safety Program, Logan and Gold Coast Faster Rail, The Wave (Stage 1), Queensland Train Manufacturing Program, and Coomera Connector (Stage 1). 

The 2026–27 capital statement also includes $22.2 billion of planned projects. Under QTRIP’s reporting approach, planned projects are not assigned a total estimated cost until they reach a more advanced stage of development. As a result, the value of planned projects reported in the capital statement is not directly comparable to the project costs reported in QTRIP. The largest planned investments relate to upgrades of the state road network in the North Coast (Moreton Bay, Sunshine Coast, and hinterland areas) and South Coast (Gold Coast, Logan, and Scenic Rim) regions. 

As projects move from planned to contractually committed status, QTRIP reports their total estimated cost and includes them in the contractually committed component of the program.

Elim Beach

3. Progress of the Cross River Rail project

The Cross River Rail Delivery Authority (the Delivery Authority) is responsible for delivering the Cross River Rail (CRR) project. The project involves constructing a 10.2-kilometre rail line, including 5.9 kilometres of twin tunnels running under the Brisbane River and the central business district, and 4 new underground stations.

The Delivery Authority is also responsible for delivering a wide range of CRR-related works. These works include rebuilding 8 stations, constructing 3 new Gold Coast stations, and installing a new signalling system.

Since 2019, both the total estimated cost and planned opening date for passenger services – referred to below as ‘in-service date’ – have changed.

FIGURE 3A
Timeline of major Cross River Rail project milestones and updates
Aug 2017
Business case released:
Icon of cash notes

$6.9 bil. total cost

Icon of a stopwatch

2024

  • Core project cost: $6.9 billion for surface works, signalling, rail systems, underground stations, tunnelling, tunnel track, and acquisition of land. Funding included $5.4 billion from the state and $1.5 billion from the private sector.
  • Additional stations and signalling works were identified for future consideration to support enhanced service levels.
Apr 2019
Three major work packages announced:
Icon of cash notes

$8.1 bil. total cost

Icon of a stopwatch

2025

  • Core project cost: $6.9 billion.
    1. Tunnel, Stations and Development (TSD): $4.2 billion ($2.7 billion state-funded and $1.5 billion privately funded).
    2. Rail, Integration and Systems (RIS): $0.8 billion state-funded.
    3. Other state-funded works: $1.9 billion for land acquisition, contingencies, and other project costs.
  • Associated project cost: $1.2 billion, including $634 million for European Train Control System (ETCS) and $600 million for RIS, both funded by Queensland Rail, bringing the overall CRR project cost to $8.1 billion.
Mar 2023
Cost increase and revised opening date:
Icon of cash notes

$9.5 bil. total cost

Icon of a stopwatch

2026

  • Core project cost: $7.8 billion, including $960 million in additional state funding ($6.3 billion state funded and $1.5 billion privately funded). The increase reflects supply chain pressures and higher material and labour costs. The revised in-service date changed to 2026.
  • Associated project cost: $1.7 billion of other state-funded works, including complementary works and ETCS, bringing the overall CRR project cost to $9.5 billion.
Dec 2024
Estimated costs and revised opening date:
Icon of cash notes

>$17 bil. total cost

Icon of a stopwatch

2029

  • Core project cost: $10.6 billion, including $0.2 billion to continue construction on the TSD package while final negotiations were underway, and $2.6 billion for future operations and maintenance.
  • Associated project cost: $6.5 billion, including $1.75 billion for expected but not yet agreed costs, bringing the overall CRR project to more than $17 billion.
  • Increase in reported total project cost reflects the inclusion of additional cost items not previously in the estimate, including tunnel integration with the existing rail network, train stabling facilities, signalling systems, temporary bus services during construction, and maintenance equipment.
Oct 2025
Cost increase and revised opening date:
Icon of cash notes

$19 bil. total cost 

Icon of a stopwatch

2029

  • Core project cost: $12.4 billion, following negotiations with delivery partners for the TSD and RIS packages during 2024 and 2025. This includes $1.8 billion in additional state funding provided for the TSD and RIS work packages. The revised in-service date changed to 2029.
  • Associated project cost: $6.6 billion, including $1.4 billion in additional funding from Queensland Rail and the Department of Transport and Main Roads, bringing the overall CRR project cost to $19 billion.
Jun 2026
Negotiations completed and estimated costs confirmed:
Icon of cash notes

$19 bil. total cost

Icon of a stopwatch

2029

Following completion of negotiations with delivery partners for the TSD and RIS packages, the total estimated cost and in-service date remained consistent with the October 2025 estimate.

Compiled by the Queensland Audit Office from Cross River Rail Delivery Authority management reports and Queensland Government ministerial statements.

1

The announced estimated total cost for the project has changed over time. Figure 3B shows the movement in the announced total estimated cost, with a focus on the changes that occurred during the 2024–25 and 2025–26 financial years. The 2026–27 announced total estimated cost reflects the completion of negotiations with delivery partners and agreement of the estimated costs to complete the project.

FIGURE 3B
Announced Cross River Rail project costs for the financial years 2022–23 to 2026–27
Stacked bar graph showing announced Cross River Rail project costs for the financial years  2022–23 to 2026–27

Compiled by the Queensland Audit Office from Cross River Rail Delivery Authority management reports and Queensland Government ministerial statements.

1

Cross River Rail is moving into testing and commissioning

In Major Projects 2025 (Report 8: 2025–26), we reported that the Delivery Authority had completed negotiations with its major contractors. These negotiations confirmed revised project costs and a revised delivery program, with first passenger services expected in 2029.

As Figure 3B shows, the estimated total cost of the CRR project and its associated works remained stable at $19 billion in 2026–27, following the completion of these negotiations.

The estimated cost of the core project remained at $12.4 billion. Complementary and associated works, including the European Train Control System, remained at $3.6 billion. Other associated project costs also remained unchanged at $3 billion in 2026–27.

The project is moving from construction into integration, testing, and commissioning. The Delivery Authority, Queensland Rail, the Department of Transport and Main Roads, and major contractors are working together to integrate and test trains, stations, signalling, and other rail systems. A dedicated ‘lead integrator’ function within the Delivery Authority is coordinating this work.

In 2026–27, the Delivery Authority expects to begin integrated onsite testing, including running trains through the tunnels and stations under controlled conditions, initially at low speeds. Construction and fit-out activities will continue while testing is underway.

Before passenger services can begin, the project must complete further train testing, staff training, operational exercises, safety assurance, and regulatory review. This work must demonstrate that the railway can operate safely and reliably. Passenger operations are still expected to start in 2029.

Project delivery timeline

Figure 3C outlines the revised timelines for the major work packages, based on information provided by the Delivery Authority.

FIGURE 3C
Cross River Rail project – progress and plan
Infographic describing the Cross River Rail project – progress and plan

Notes: TSD – Tunnel, Stations and Development; RIS – Rail, Integration and Systems; ETCS – European Train Control System.

Refer to Figure D1 in Appendix D for the project details.

Compiled by the Queensland Audit Office from Cross River Rail Delivery Authority management reports.

1

Project milestones achieved during the year

The Delivery Authority continued to progress work across the project’s major packages during 2025–26. The twin tunnels are complete, and the 4 underground stations are nearing completion. During the year, work progressed on station entrances, internal finishes, mechanical and electrical systems, communications equipment, and platform screen doors. Static (or stationary) testing also commenced at the underground stations.

Above ground, the Delivery Authority handed over Salisbury station to Queensland Rail, bringing the number of station handovers to 6 of 7. Pimpama and Hope Island stations opened during the year, while construction continued at Merrimac station.

For the European Train Control System (ETCS) package, testing of the signalling system continued on the Shorncliffe line, and Queensland Rail began staff training on the new train control systems.

Additional funding for Cross River Rail-associated projects

Several projects the Delivery Authority is delivering are on behalf of the Department of Transport and Main Roads and Queensland Rail. These include:

  • upgrades to train stabling yards, bridges, and stations, funded through Queensland Rail’s capital program under the Complementary and Associated Works package
  • implementation of the ETCS, also funded through Queensland Rail’s capital program
  • construction of the Pimpama, Hope Island, and Merrimac stations on the Gold Coast, delivered under the New Gold Coast Stations project.

As part of the broader SEQ Rail Connect strategy, which aims to deliver a more integrated transport network across South East Queensland, additional rail infrastructure projects are still being planned to complement and support CRR.

Figure 3D outlines the major rail and associated projects linked to CRR, including their funding sources, budget changes, and spending to date.

FIGURE 3D
Major rail and associated infrastructure projects (estimated expenditure as at 30 June 2026)
Infographic showing major rail and associated infrastructure projects (estimated expenditure as at  30 June 2026)

Notes:

1 The Delivery Authority capital budget for the CRR project (including private finance) is $9.825 billion. The revised budget relates to finalisation of negotiations completed during 2026 with the contractors delivering the TSD and RIS package.

2 In 2026, the state committed additional funding of $918 million for the TSD work package.

3 The total budget for the RIS work package is $3.6 billion, with Queensland Rail funding $2.2 billion and the Delivery Authority funding $1.4 billion. The revised budget relates to finalisation of negotiations completed during 2026 with the contractors delivering the RIS package. These balances have been sourced from Delivery Authority reports, and there may be minor differences in expenditure due to accounting treatment.

4 The total budget for the ETCS work package is $1.4 billion, fully funded by Queensland Rail. This balance has been sourced from Delivery Authority reports, and there may be minor differences in expenditure due to accounting treatment.

5 The total budget for New Gold Coast Stations is $591 million, with the Department of Transport and Main Roads contributing $518 million and Queensland Rail contributing $73 million.

6 The total budget for the ETCS Level 2 signalling technology between Beenleigh and Varsity Lakes is $339 million, fully funded by Queensland Rail. The project is being delivered by the Department of Transport and Main Roads, with support from Queensland Rail.

7 The total budget for the ETCS Level 2 signalling technology between Kuraby and Beenleigh is $326 million. The project is being delivered by the Department of Transport and Main Roads, with support from Queensland Rail.

8 This project was previously known as the Direct Sunshine Coast Rail Line (Stage 1) and will deliver a 19-kilometre dual-track rail line from Beerwah to Caloundra. The total budget for Stage 1 is $5.5 billion.

9 The total budget for the Logan and Gold Coast Faster Rail is $5.75 billion, funded equally by the Australian and Queensland governments.

10 This represents the revised budget for the Queensland Train Manufacturing Program, following the completion of a tender process in 2023. The 2026–27 capital statement includes a component of this overall budget, being $4.9 billion for the manufacturing phase.

NGR – New Generation Rollingstock; SEQ – South East Queensland.

All budgets for major projects include a contingency to allow for any construction risks to be addressed as they arise. For the CRR project, this is included in the Other works revised budget of $2.4 billion. As of 30 June 2026, the contingency for the CRR project remained within the revised budget.

Budget figures reflect the latest approved budget or revised budget. Where multiple budget figures are presented, each reflects the approved or reported budget at the relevant date and has not been restated for subsequent changes.

Compiled by the Queensland Audit Office from Cross River Rail Delivery Authority management reports, information from the Department of Transport and Main Roads, and from the 2026–27 capital statement.

1